Hoppa till huvudinnehåll

Svenska kraftnät använder kakor (cookies) för att förbättra och anpassa ditt besök på vår webbplats. Genom att använda webbplatsen accepterar du användandet av dessa kakor. Läs mer om kakor och hur du avaktiverar dem

Nordic Grid Development Plan 2019

The four Nordic TSOs publish a common Nordic Grid Development Plan every other year and the NGDP for 2019 is now available. The report describes the main drivers of the changing Nordic power system, and the planned and on-going grid developments introduced to meet the continually changing demands challenging the Nordic transmission grid.

Today, the transmission system operators (TSOs) of Finland, Sweden, Denmark and Norway launched the Nordic Grid Development Plan 2019. The study contains a collective reporting of current plans and grid development projects across the Nordics and presents a common view on the overall development of the future Nordic power system. In addition, some mutually coordinated studies on possible future grid investments in five Nordic corridors are presented.

The NGDP 2019 meets the request of the Nordic Council of Ministers for a joint Nordic grid development plan. The Nordic Grid Development plan will continue to be updated every second year, as part of the greater and more holistic cooperation described in the report “The way forward – Solutions for a changing Nordic power system”.

The NGDP 2019 report describes the changing functionality required of the grid in the future. The main drivers of Nordic grid development identified in the plan are increased volatility due to massive increase in renewable generation, decommissioning of fossil fuel facilities, growth in consumption from increased electrification and new industries, aging equipment and the need for reinvestments in existing grid assets, new interconnectors with Continental Europe and decommissioning of nuclear plants in Sweden. These regional drivers of grid development have led to a very substantial increase in grid investments by the Nordic TSOs. At the same time, several measures are being developed to make electricity markets and system operation more effective.

The 2019 plan includes an early assessment study of five Nordic corridors, which focused on market simulations, market benefits and high-level analyses of capacity in the corridors. The five corridors were initially identified in NGDP 2017, and bilateral studies for each corridor were prepared based on a common evaluation framework and Nordic reference scenario, including planned internal reinforcements in each country. The studies show an early outlook for possible future grid investments in the five corridors, revealing potential to further strengthen capacity between Nordic countries.  

With a highly interconnected power system, it is important to continue the Nordic coordination and cooperation on both grid planning and studies. The energy sector is changing rapidly, and as the sector becomes more complex, it will be important to continue to study how the Nordic countries can support each other. A strong grid enables power from renewable generation to fully enter the market, replacing generation from fossil fuels and thus enabling a fully fossil-free generation portfolio, concludes the report from the Nordic Planning Group. The Nordic Planning Group (NPG) is a joint grid planning group consisting of members from the four TSOs.

 

----------------------------------------------------------------

The way forward - Solutions for a changing Nordic power system” report was published in March 2018. Since its publication, the Nordic TSOs have been working to develop the solutions identified in cooperation with stakeholders. The next Solutions Report update will be published in the spring of 2020.

 