Svenska kraftnät and the other Nordic Tranmission System Operators (TSO) will introduce new harmonised technical requirements for the ancillary services Frequency Containment Reserve Normal, (FCR-N), Frequency Containment Reserve Disturbed, Upwards (FCR-D up) and for Frequency Containment Reserve Disturbed, Downwards, (FCR-D down). Svenska kraftnät is now holding an open consultation on the future technical requirements for the relevant support services FCR-N, FCR-D up and FCR-D down.
In case of questions regarding the consultation, please e-mail malin.wester@svk.se.
Answer the consultation
Provide your feedback via e-mail to project manager Malin Wester via e-mail: malin.wester@svk.se.
Revised proposition: FCR Techical Requirements (.pdf) Opens in a new window
Read about the consultation and answer it in Swedish
More information
The updated requirements proposal is presented at a Nordic workshop
On 28 March, the Nordic TSOs will host a workshop to present and discuss the future technical requirements for the ancillary services FCR-N, FCR-D up and FCR D down. Pre-registration no later than 18 March is required.
During the meeting, results and experiences from the tests performed during the pilot phase for the new technical requirements will be presented. We will also discuss the Nordic TSOs' revised proposition for new technical requirements.
Read more and register to the webinar no later than 18 March on the event page
Summary of changes in the revised proposition for technical requirements for FCR
The changes can be summarised in four important parts.
- Reduced number of tests
The test program is greatly shortened for both FCR-N and FCR-D. For FCR-D, the ramp test has been modified to include deactivation and parameter switching tests. - Relaxation of the requirements
The requirements for the FCR-N have been relaxed somewhat by assuming a slightly higher frequency-dependent load in the system. It will also be possible to pre-qualify a scaled-down capacity if the performance requirements are not fully met. The requirements for FCR-D have been relaxed both in terms of performance and stability. - Clarified requirements for resources with limited energy reserve, LER
The requirements include, among other things, state of charge management. - New documentation structure
The structure of the documentation has also been changed. The previous versions included a separate supporting document. It has now been removed, and the key content has been merged with the technical requirements document.
The new proposition is based on joint development and practical tests
The current proposition for new technical requirements for FCR has been developed in a joint Nordic TSO-project assisted by a reference group consisting of Nordic energy market participants.
In 2021, a test phase was held where suppliers were allowed to carry out tests to try to meet the proposed new technical requirements. In connection with the test phase, the TSOs collected the participants' experiences and views on both requirements and test procedures. The proposition for technical requirements has since been updated based on the experiences during the test phase. It is this revised document that is now open to consultation.
The process ahead
Svenska kraftnät are now collecting feedback on the draft proposition for new technical requirements. The Nordic project will then, if necessary, update the proposition for new technical requirements based on the feedback. Thereafter, the Nordic TSOs will prepare a legal method proposition based on the propositioned requirements.
Public consultation of the legal method proposition
The legal method proposition will be published for public consultation and then submitted to the national supervisory authorities in the Nordic countries for approval.
Contact
For questions to Svenska kraftnät, contact project manager Malin Wester via e-mail: malin.wester@svk.se.