We are strengthening the Swedish national grid with new lines and stations to take care of new wind power, eliminate limitations in the grid and to meet society's demands for a secure electricity supply.


Skåne

Öresund cables

Svenska kraftnät is planning to replace the southern of the two submarine cabled between Sweden and Denmark. The connection is reaching its technical lifetime and is important for the electricity supply in both Sweden and Denmark.

Skåne county

Hansa PowerBridge

We are planning the new power connection Hansa PowerBridge between Hurva station in Hörby municipality and Northern Germany. The strong link between Scandinavia and Germany supports a more climate-friendly European power generation while securing the electricity supply in Southern Sweden.

NordSyd

NordSyd

NordSyd – powerful reinforcements between electricity price areas 2 and 3. The boundary between electricity price areas 2 and 3, what is known as intersection 2, will be renewed and reinforced over the next 20 or so years thanks to powerful investments.

Southeastern Sweden

Ekhyddan – Nybro

We are planning a new overhead line between Ekhyddan in Oskarshamn municipality and Nybro in Nybro municipality. The new overhead line will contribute to creating a more reliable power grid, both on a regional and national level.

Southeastern Sweden

Nybro – Hemsjö

We are planning a new overhead line between Nybro in Nybro municipality and Hemsjö in Olofströms municipality. The new overhead will contribute to creating a more reliable power grid, both on a regional and national level.

Kalmar county

NordBalt

We strengthen the connection between the Nordic and Baltic electricity market with an electricity connection to Lithuania

Western Götaland

Skogssäter – Stenkullen

We are planning a new line between Skogssäter in Trollhättan municipality and Stenkullen in Lerum municipality in order to ensure the electricity supply in Western Götaland

Southern Sweden

The SouthWest Link

Our biggest investment ever that extends from Närke to Skåne. With the link in full operation, the capacity to transmit electricity from central to southern Sweden is expected to increase by up to 25 percent.

Western Norrland

Storfinnforsen – Midskog

We plan to rebuild the world's oldest 400 kV line between Storfinnforsen and Midskog in order to receive electricity from new wind farms in the area.

Västernorrland county

Långbjörn – Storfinnforsen

We are planning a new AC line between Långbjörn and Storfinnsforsen to reinforce the grid in Sollefteå Municipality.

Örebro

Lindbacka – Östansjö

We plan to build a new line between Linbacka and Östansjö to reinforce the grid in Eastern Svealand. 

Stockholm

Snösätra – Ekudden

With the new electricity connection between Snösätra and Ekudden we are reinforcing the national grid in the Stockholm region. This is part of the project Stockholms Ström designed to meet the region’s growing need for electricity.

Stockholm

Anneberg – Skanstull

With the new electricity connection between the stations Anneberg and Skanstull we are reinforcing the grid in the Stockholm region. It is part of the project Stockholm Ström designed to meet the region's growing electricity needs.

Stockholm

Örby – Snösätra

With the new electricity connection Örby and Snösätra we are reinforcing the national grid in the Stockholm region. It is part of the project Stockholm Ström designed to meet the region's growing electricity needs.

Northern Sweden

Messaure - Keminmaa

The national grid operators in Sweden (Svenska kraftnät) and Finland (Fingrid) have planned the construction of a 400 kV AC power line between Messaure in Sweden and Keminmaa on the Finnish side.