Business packages for overhead power line contracts with execution contract
The business packages in the execution contract that are intended to be procured in 2025-2026:
Business packages | Execution time | Procurement are to be published |
---|---|---|
Uppsala South (.pdf) Opens in a new window | 4 years | 2026 Q1 |
Uppsala North (.pdf) Opens in a new window | 6 years | 2026 Q1 |
More about business package Uppsala
The Uppsala package is divided into Uppsala South and Uppsala North, and includes both new construction and dismantling. The new power lines will modernize the national grid, while increasing the transmission capacity in the grid to enable increased power output in the area.
The power lines are being built as two parallel overhead lines of 400 kV over a distance of approximately ten kilometers, as well as approximately ten kilometers of overhead line of 220 kV. We will also build a shorter distance with underground cable, and dismantling 160 kilometers of old power lines that are approaching the end of their technical life-span.
View presentation of business package Uppsala (.pdf) Opens in a new window
Timetable
- Procurement of business packages published Q1 2026
- Contract award Q3 2026
- First contract begins 2026
- Establishment of first project 2026
- Implementation period 6 years
Scope
- 10 km overhead line 220 kV
- 100 km double overhead line 400 kV
- 160 km dismantling overhead line 220 kV
- 0.5 km underground cable 220 kV
More information about included projects
Information about the projects are only avaliable in swedish.